What a First Article Inspection Report (FAI) Should Include

A First Article Inspection Report (FAI) is the acceptance basis before CNC machined parts enter mass production. Buyers use this document to confirm that part dimensions, materials, processes, and specifications meet the drawing and procurement requirements. A complete FAI must be traceable to every critical characteristic and be jointly signed off by the machining supplier and the buyer. For buyers, the FAI is not just a shipping document; it is the first checkpoint for assessing whether a machining supplier has the stability for mass production.

Core Purpose of the FAI Report

The core purpose of the FAI is to 'use one part to represent all'—that is, using the first production part as a sample to verify whether the supplier's process capability, measuring equipment, and quality control records can be consistently replicated in subsequent batches. For OEM buyers and Tier-1 suppliers, passing the FAI means the process is frozen and mass production can begin; failing it means the process is not yet under control and requires rework or resubmission. When reviewing an FAI, buyers should treat it as evidence of the supplier's process maturity, not merely a dimensional report.

Items an FAI Report Should Include

  • Basic Identification Information

    Part number, material code, batch, customer name, supplier name, report date, and report number—none can be omitted.

  • Drawing Revision and Specification References

    State the engineering drawing revision, technical specifications, and international standards used to avoid disputes from version mismatches.

  • Material Certification and Traceability

    List the material grade, supplier, and material test certificate (MTC) number to ensure consistency with the buyer-specified material.

  • Process and Equipment Records

    Note the CNC machine model, machining operations, tooling, and program versions used to aid process parameter traceability.

  • Full Dimensional Measurement Results

    List all measured values, tolerances, and pass/fail judgments for every dimension per the drawing; critical characteristics must include measurement reports.

  • Visual and Functional Inspection

    Results and judgments for surface roughness, threads, hole positions, mating dimensions, and other visual and functional checks.

  • Measuring Equipment and Traceability

    State the measuring instruments used (e.g., CMM, projector), calibration dates, and traceability numbers.

  • Sign-off Fields

    Signature fields for the supplier's quality assurance, process engineering, and the buyer's representative to confirm both parties are accountable for the results.

Common Deficiencies Buyers Find When Reviewing FAIs

In practice, the most common deficiency in FAIs is not dimensional nonconformance but 'traceability breaks'—for example, missing material certificates, expired calibration dates on measuring equipment, unstated drawing revisions, or critical characteristics only sampled rather than fully inspected. Another common issue is 'data without judgments,' where buyers must interpret pass/fail themselves, increasing communication costs. When receiving an FAI, buyers should first check traceability completeness, then review dimensional data, and finally look at sign-offs—this quickly filters out suppliers that lack mass production capability.

How to Agree on FAI Format with the Machining Supplier

Buyers can request an FAI template from the supplier during the quotation stage and specify the format (e.g., AS9102 or a custom template). If the buyer has their own FAI template, it should be provided in the RFQ to avoid rework after the supplier submits in their own format. For CNC machined parts, critical characteristics (KPCs) typically include dimensional tolerances, geometric dimensioning and tolerancing (GD&T), and surface roughness; these items must be listed individually in the FAI and cannot be omitted.